For this project we were required to do 3 bores for a 150 PVC sewer diversion for Melbourne Grammer to allow the new Metro Tunnel station to be built. They consisted of an 87 and 52 meter shot up St Kilda road and a 57 meter shot under St Kilda road.
Bore size: 380mm OD
Pipe installed: Iplex DN150 PVC RESTRAIN™
Ground Conditions: Sandy Clay
Shaft Depths: 3 - 4 meters
Date
November, 2017
Client
Adept Civil Group
Category
Free Boring